8.2 Project management 2025-05-07 - future
gantt
title Mining Rig Monitor
dateFormat YYYY-MM-DD
section Commander
write api document for expected_status for asic sentry :done, a1, 2025-05-07, 2025-05-08
implement api for asic_sentry expected_status :done, a2, 2025-05-08, 2025-05-09
unit test for asic expected_status :done, a3, 2025-05-08, 2025-05-09
implement UI for user to control asic/light :done, a4, 2025-05-09, 2025-05-10
unit test UI for user to control asic/light :done, a6, 2025-05-09, 2025-05-10
change logo :done, a7, 2025-05-10, 2025-05-12
do code refactor + unit test for all module :a5, after a4, 1w
Milestone 5.0.0 :milestone, after a4, 1d
section ASIC Sentry
write api document :done, b1, 2025-05-07, 2025-05-08
create CI/CD for asic-sentry-api-docs :done, b2, 2025-05-07, 2025-05-08
migrate ASIC Sentry to Nexus Dashboard UI :done, b3, 2025-05-10, 2025-05-11
milestone 2.0.0 Migrate to Nexus Dashboard :milestone, 2025-05-11, 2025-05-11
implement get & update expected_status from commander :done, b4, 2025-05-12, 2025-05-13
implement api return expected_status for RRC :done, b5, 2025-05-13, 2025-05-14
implement UI to map asic miner and RRC :done, b6, 2025-05-13, 2025-05-14
Milestone 3.0.0 Suport RRC :milestone, 2025-05-14, 2m
section Remote Relay Controller
draft specfification docs :done, c1, 2025-05-07, 1d
design electronic schematic :c2, after b6, 1d
implement feat. on/off asic miner 7.2.1 :c3, after c2, 7d
implement feat. on/off light bulb 7.2.2 :c4, after c3, 7d
Milestone 1.0.0 On/Off ASIC & Light :milestone, after c4, 1d
implement feat. current sensor :c5, after c4, 7d
implement feat. display LCD :c6, after c5, 7d
Milestone 2.0.0 :milestone, after c6, 1d
Press "Alt" / "Option" to enable Pan & Zoom